Acute Mental Health Unit Project
The establishment of a new purpose-built Acute Mental Health facility is well underway. Construction commenced in Febraury 2023 and by August the foundation was complete. By December, the large structural beams were in place and roofing has begun. The forecast completion date is June 2025, and the budget $66.6 million.
The new unit will have 28 beds, and is 2,900 m2 in size. Looking to the future, there is provision for four to eight beds to be added. The building was design was inspired by the nearby mountain ranges - the Tararuas and the Ruahines. It will be welcoming, warm and make good use of natural light to enhance the therapeutic nature of care.
View the image gallery below to see the progress made.
Progress as 11 October 2024
Key to the design of our new facility is to provide a home-like environment, and to make use of natural light with windows, glass, indoor courtyards and skylights. Now more scaffolding is being removed the domestic style exterior finish can be seen.
Take another walk through our new acute mental health unit …
Take part in this virtual tour of our new Acute Mental Health Unit which is currently under construction. Not only will you get to see the work within, you will also get to see it from above. Courtesy of the main contractors, LT McGuiness, this virtual tour is brought to you to show progress as at the beginning of June 2024. Enjoy.
February 2024 video tour
September - December 2024
Key to the design of our new facility is to provide a home-like environment, and to make use of natural light with windows, glass, indoor courtyards and skylights. These elements can now be seen as the building work progresses.
May - August 2024
Construction continues and by the end of August much of external scaffolding has been removed
1 Jan - 3 May 2024
Construction continues - roof completed
The new building is taking shape and work continues on the external cladding, the roof, and the interior structure.
Sep - Dec 2023 | Framing & construction
Framing and construction of the building began in September, and the large structural frames were in place by the end of the year. The design vision for the roof takes its inspiration from the nearby mountain ranges of the Tararuas and the Ruahines – made of high wooden interior ceilings to reflect the influence of the landscape.
Feb – Aug 2023 | Foundations completed
The foundation for our new Acute Mental Health Unit was completed on 23 August 2023, and took six months in total.
Aug 2022 - Jan 2023 | Construction site cleared
Ahead of the construction crew commencing work, the building site was cleared of buildings and trees. Pullar Cottage (previously used for doctors’ accommodation) was removed as a result of poor condition ruling out relocation. However, thanks to a deconstruction approach its lovely matai flooring, doors and window frames were able to be re-purposed. In addition to the surrounding trees that were required for removal, a plan for transferral was done in partnership with Pae Ora and local iwi. Many were transferred to other areas of the campus, while the large Totara tree was given to Rangitāne to be used for carvings that will form part of the new facility.
Feb 2020 - Sep 2023
The beginning - turning a concept into a detailed design
In February 2020 a concept design was developed. Government approval for the business case was received in September 2020. By March 2021, architects were appointed, and work on te preliminary design got underway. Preparations for developed design then began in October 2021. In June 2022 a cultural narrative was put in place to support the detailed design. This was Te Wao-nui-a-Tane, which translates as “The Great Forest of Tane” It reflects the ecosystem of integrated health. By September 2022 the detailed design was completed and procurement of a main contractor got underway.